Four Winds Construction Update Dec 2013

Greetings!

We are glad to inform you the latest update regarding our building process! As we approach 2014, the momentum of our construction continues to grow towards our "Intelligently Beautiful Design"

The architects of our apartment have created a design with a birds-eye view concept of our property in order to provide you a sense of the space and assist you in conceiving the design, which is in all aspects exclusive.

Four Winds of Senayan is currently undergoing the following construction process :

  • Drilling and foundry work on the pile foundation is still ongoing, with more than 100 points and is expected to be completed by the end of December 2013.
  • Contiguous pile retaining wall.
  • The temporary site facilities include fabrication area, and storage areas have been completed since the third week of November 2013.
  • Construction of location offices and the creation of temporary access roads have been completed this month.
  • Implementation and supervision of health and safety procedures.
  • Mud and soil disposal as a result of drilling will be completed by the end of December 2013.
  • Excavation of land for the building of the underground parking lot will begin on January 2014. Our construction process will continue in order for Four Winds of Senayan to be completed as planned. Parking lot is provided for apartment owners and their respective guests. Safety and comfort is guaranteed at every parking area of Four Winds Senayan.

During this month, our construction team continues to work hard in order to complete the best building process for you but will go on a break on January 1st, 2014.

If you have any questions in relation to your apartment purchase at Four Winds of Senayan, please feel free to contact us at +62 21 9197 0077 and +62 21 9197 0088 or email us at info@fourwinds.co.id




Sincerely yours,


Derijanto Gani
Project Director