Four Winds of Senayan Construction update June 2015

This is the latest update and information details about Four Winds of Senayan as of June 11th, 2015 with details follows :

Finishing Work :

  • Wall finishes and UPVC windows 15th floor is still ongoing.
  • Ceiling work is still ongoing on 7th and 8th floor.
  • Marble work is still ongoing on 6nd floor and 7rd floor.
  • Finishing façade curtain wall and aluminum composite panel all area.
  • Precast concrete wall work is still ongoing on 16th floor.
  • Fence external area / landscape work is still ongoing.
  • Installation sanitary and Shower glass partition.
  • Installation kitchen cabinet and wardrobe.

ME Occupation :

  • Installation Fire Fighting and plumbing work is 11th floor.
  • Installation refrigerant AC work is 12th floor.
  • Ducting and box hydrant work is still ongoing on 10th floor.
  • Electrical wiring and electronic work is still ongoing on 12th and 13th floor.

If you have any questions in relation to your apartment purchase at Four Winds of Senayan, please feel free to contact us at +62 21 9197 0077 and +62 21 9197 0088 or email us at info@fourwinds.co.id

Alternatively feel free to contact us directly on the details below : PT. Tri Tirta Permata
The Belleza Shopping Arcade, 1st Floor # 08
Jl. Letjen Soepeno No. 34 Arteri Permata Hijau
Jakarta Selatan 12220
T. +62 21 2991 6020
F. +62 21 2991 6021
E. info@fourwinds.co.id

Sincerely yours,


Derijanto Gani
Project Director