Four Winds Construction Update March 2014

Greetings!

We would like to keep you abreast with the latest development of our "Intelligently Beautiful Design" and the progress of its construction as of March 2014 as follows:

  • Work on the excavation of the basement is still ongoing
  • Work on wall retentions to increase elevation
  • Installation and raising of tower cranes for work equipment, the lifting of materials, and others to quicken the construction process
  • Structural work of the ground water tank and water reservoir supplies from PAM to supply water in the event of a fire.
  • Ground anchor work to reinforce and strengthen wall retentions, through tying or nailing the wall retentions to the ground so that it remains safe and structured throughout the excavation process.

Furthermore, we would like to inform you of the progress of the marketing gallery, which is located nearby Four Winds of Senayan, with the following details:

  • Work on the roof and walls of the marketing gallery area is still underway
  • Work on the wall areas for the elevators.

If you have any questions in relation to your apartment purchase at Four Winds of Senayan, please feel free to contact us at +62 21 9197 0077 and +62 21 9197 0088 or email us at info@fourwinds.co.id




Sincerely yours,


Derijanto Gani
Project Director

Copyright by © www.fourwinds.co.id