Four Winds of Senayan Construction Update September 2014

This is the latest update and information details about Four Winds of Senayan as of September 15th, 2014 with details follows :

  • Build temporary facilities.
  • Column structure work, shear wall, corewall from 1st floor to the 2nd floor.
  • Slab structure and beam on 2nd floor.
  • Column structure work, shear wall, corewall from 2nd floor to the 3rd floor.
  • Slab structure and beam on 3rd floor.
  • Column structure work, shear wall, corewall from 3rd floor to the 4th floor.
  • Slab structure and beam on 4th floor.
  • Finishing ceiling exposed basement work is still ongoing.
  • Wall finishes basement work for finishing is still ongoing.
  • Finishing floor hardener work is still ongoing.
  • Column finishing work on parking area is still ongoing.
  • Installation of the sleeve pipe work is still ongoing.
  • Support work for ducting and cable tray is still ongoing.
  • Installation of the pipe work is still ongoing.
  • Implementation of health and safety procedures.

If you have any questions in relation to your apartment purchase at Four Winds of Senayan, please feel free to contact us at +62 21 9197 0077 and +62 21 9197 0088 or email us at info@fourwinds.co.id

Alternatively feel free to contact us directly on the details below :
PT. Tri Tirta Permata
The Belleza Shopping Arcade, 1st Floor # 08
Jl. Letjen Soepeno No. 34
Arteri Permata Hijau – Jakarta Selatan 12220
T. +62 21 2991 6020 / +62 21 9559 0077 / +62 21 9559 0088
F. +62 21 2991 6021
E. info@fourwinds.co.id

Sincerely yours,


Derijanto Gani
Project Director

Copyright by © www.fourwinds.co.id